Friday, 14 June 2013

Software Engineering MCQ

1.
Identify, from among the following, the correct statement.
(a)   One of the main challenges Software Engineering facing today is the requirement of most software systems to work with a multitude of homogenous systems
(b)   ‘Legacy systems’ are custom developed software systems for the legal domain
(c)   Software does not wear-out in the traditional sense of the term, but software does tend to deteriorate as it evolves
(d)   Since software is essentially ‘intangible’ it is relatively easy to manage software projects
(e)   With the advent of component based software assembly, we find that only less than 20% of today’s software is still custom built.
2.
Software Engineering:
(a)   Is a set of rules about developing software products
(b)   Has been around as a discipline since the early 50’s
(c)   Started as a response to the so-called ‘Software Crisis’ of the late 90’s
(d)   Is an engineering discipline concerned with all the aspects of software production
(e)   Is now a mature discipline on par with other established engineering fields.
3.
Read the following paragraph and identify the correct statement.
“Imagine that you were recently hired as a software engineer to a company that specializes in aircraft navigation control software. While orientating yourselves to the company’s work practices, you observe that they in fact do not conduct a few tests that they should in order to comply with the relevant safety standard. When you inquire about this from the project manager, he dismisses it saying that those tests are really unnecessary (and takes an unreasonably long time to conduct, as well as being superfluous) and that they have managed with the other tests for so long, without any problems.”
(a)   You should immediately resign from the company and file a complaint with the relevant standard institution
(b)   You should do nothing and let the matter slide
(c)   Although you are new to the company, and you hardly know anything about the internal processes and politics, you should insist on the company changing its work practices immediately; failing which you threaten to report the matter
(d)   Since you are new to the company, and you are unfamiliar with the internal processes and politics, you should first find-out more about the issue and its background
(e)   None of the above statements are correct.
4.
With regard to Evolutionary development, identify the correct statement.
(a)   Evolutionary development usually comes in two flavors; exploratory development, and throw-away prototyping
(b)   Very large projects are natural candidates for an evolutionary development based approach
(c)   Exploratory development is used in situations where most of the requirements are well understood in advance
(d)   One of the strong points of evolutionary development is that it facilitates easy project management, through the high volume of documentation it generates
(e)   Often the construction of a throw-away prototype is not followed by a reimplementation of the system using a more structured approach.
5.
What is the fundamental reason that software cannot be considered to be engineered?
(a)   It is designed by humans and therefore flawed
(b)   Software engineering (as opposed to other forms of engineering, such as Civil) is an art - not a science
(c)   The discipline is relatively new, say in comparison to bridge building that is an activity that has millennia of practice
(d)   None of these are true. Software Engineering is a truly rigorous discipline
(e)   The complexity of systems and their interaction continues faster than we can understand it.
6.
The software life cycle can be said to consist of a series of phases. The classical model is referred to as the waterfall model. Which phase may be defined as "The concept is explored and refined, and the client's requirements are elicited?"
(a)  Requirements                                   (b)  Specification                                    (c)  Design
(d)  Implementation                                 (e)  Integration.
7.
The individual or organisation who wants a product to be developed is known as the:
(a)  Developer           (b)  User                  (c)  Contractor          (d)  Initiator              (e)  Client.
8.
Which of the following items should not be included in the software project management plan?
(a)   The techniques and case tools to be used
(b)   Detailed schedules, budgets and resource allocations
(c)   The life cycle model to be used
(d)   The organisational structure of the development organisation, project responsibilities, managerial objectives and priorities
(e)   All of the above.
9.
The final form of testing COTS software is _________ testing.
(a)  Unit                   (b)  Integration          (c)  Alpha                (d)  Module              (e)  Beta.
10.
In the maintenance phase the product must be tested against previous test cases. This is known as __________ testing.
(a)  Unit                   (b)  Integration          (c)  Regression        (d)  Module              (e)  Beta.
11.
Which property of the rapid prototype is not important?
(a)   The speed with which it can be developed
(b)   The speed with which it can be modified
(c)   Its ability to determine the client's real needs
(d)   The insights that the design team can gain from it, even if they are of the 'how not to do it' variety
(e)   Its internal structure.
12.
An example of the risk involved in software development is
(a)   Key personnel may resign before the product is complete
(b)   The manufacturer of critical components (e.g. the hardware associated with a real-time system) may go bankrupt
(c)   Technology changes may render the product obsolete
(d)   Competitors may market a fully functional lower-cost equivalent package
(e)   All of these are risks involved in software development.
13.
A simple way of looking at the spiral software life-cycle model is as a waterfall model with each phase proceeded by
(a)  Build-and-fix                                     (b)  Freezing            (c)  Synchronization
(d)  Testing                                            (e)  Risk analysis.
14.
The degree of interaction between two modules is known as
(a)  Cohesion           (b)  Strength            (c)  Inheritance        
(d)  Coupling            (e)  Instantiation.
15.
The relationship between a derived class (or subclass) and base class is referred to as
(a)  Association                                      (b)  Inheritance         (c)  Polymorphism   
(d)  Instantiation                                     (e)  Aggregation.
16.
Myers (1978) identifies seven levels of cohesion. Which level of cohesion may be defined as followed; "the output from one element in the component serves as input for some other element"?
(a)  Communicational cohesion                (b)  Functional cohesion                         
(c)  Communicational cohesion                (d)  Temporal cohesion                    (e)  None of these.
17.
A design is said to be a good design if the components are
(a)   Strongly coupled
(b)   Weakly cohesive
(c)   Strongly coupled and Weakly cohesive
(d)   Strongly coupled and strongly cohesive
(e)   Strongly cohesive and weakly coupled.
18.
If a control switch is passed as an argument this is an example of _______ coupling.
(a)  Content             (b)  Common            (c)  Control              (d)  Stamp               (e)  Data.
19.
Which of the following is a type of abstraction?
(a)  Data                  (b)  Procedural         (c)  Iteration            
(d)  All of the above   (e)  None of the above.
20.
In the classical chief programmer team approach, the team member responsible for maintaining the detailed design and coding is
(a)   The chief programmer
(b)   The programming secretary
(c)   A specialized function that exists outside 'the team'
(d)   The individual coder (i.e. programmer)
(e)   The back-up programmer.
21.
Internal costs include
(a)   Developers salaries
(b)   Managers and support personnel salaries
(c)   The cost of overheads such as utilities, rent and senior managers
(d)   Materials (such as manuals) and services such as travel
(e)   All of the above.
22.
Problems with using Lines of Code to measure the size of a product include(s)
(a)   The creation of source code is only part of the development effort
(b)   The Lines of Code (LOC) will differ between languages and cannot be measured for some languages
(c)   Should comments, data definitions etc (i.e. non-executable LOC) be included as well?
(d)   The final size (kLOC) can only be determined once the product is delivered
(e)   All of the above.
23.
Software Science bases its estimation of the size of a product on
(a)   Files (Fi), Flows (Fl) and Processes (Pr)
(b)   Lines of Code (kLOC)
(c)   Function Points (FP)
(d)   operands and operators
(e)   Feature Points (FeP).
24.
In Intermediate COCOMO the mode that represents complex products is referred to as
(a)  Embedded                                       (b)  Semidetached                                  (c)  Organic
(d)  Multiplicative                                    (e)  Monolithic.
25.
Work that continues throughout the project and does not relate to any specific phase of software development is termed a(n)
(a)  Milestone           (b)  Project function                                (c)  Activity             
(d)  Task                  (e)  Baseline.
26.
The advantage of following the IEEE Standard for drawing up a Software Project Management Plan (SPMP) - see IEEE Standard 1059.1 1987 - is
(a)   It is drawn up by representatives from major software development organisations
(b)   It is designed for all types of software products
(c)   It is a framework that can be used irrespective of process model or specific techniques
(d)   It can be tailored for each organisation for a particular application area, development team or technique.
(e)   All of the above.
27.
The best way to test the Software Project Management Plan (SPMP) is by
(a)  Prototyping        (b)  Inspection          (c)  Simulation        
(d)  Compilation        (e)  Debugging.
28.
Algorithmic cost estimation in different organisations may be different for the same application development, because
(a)   Different organisations consider complexity factors differently
(b)   Different organisations may use different programming languages
(c)   Developers' skills may vary
(d)   Techniques for the measurement of productivity may vary
(e)   All of the above may be true.
29.
The aim of software engineering is to produce software that is
(a)   Fault-free
(b)   Delivered on time
(c)   Delivered within budget
(d)   Satisfies users' needs
(e)   All of these are the aims of software engineering.
30.
Object-oriented concepts are not new. The first OO language was considered to be
(a)  ALGOL-68                                        (b)  FORTRAN 77     (c)  C                     
(d)  MODULA                                         (e)  SIMULA 67.
31.
Software engineering is the systematic approach to the
(a)
Development of software
(b)
Operation of software
(c)
Maintenance of software
(d)
Retirement of software
(e)
All of the above.
32.
Brooks’ view of the essence of software included
(a)
People, Quality, Process and Productivity
(b)
Performance, Robustness, Maintainability and Reusability
(c)
Complexity, Conformity, Changeability and Invisibility
(d)
Efficiency, Reliability, Usability and Robustness
(e)
Accuracy, Testability, Visibility and Changeability.
33.
What is the essence of software engineering?
(a)
Requirements Definition, Design Representation,  Knowledge Capture and Quality Factors
(b)
Maintaining Configurations, Organizing Teams, Channeling Creativity and Planning Resource Use
(c)
Time/Space Tradeoffs, Optimizing Process, Minimizing Communication and Problem Decomposition
(d)
Managing Complexity, Managing Personnel Resources, Managing Time and Money and Producing Useful Products
(e)
Maintaining Communication, Managing unuseful products and Not optimizing process.
34.
Which of the following is a life-cycle concern?
(a)
Testing
(b)
Portability
(c)
Programming
(d)
Planning
(e)
All of the above.
35.
Which best captures the nature of the quality paradigm?
(a)
The Nature of Quality, A Process Perspective, Defect Elimination
(b)
Process, Product, People, Problem
(c)
Measurement, Quality Control, Validation
(d)
Feasibility, Requirements, Economics, Customer’s Needs
(e)
Analysis, Testing, Design.
36.
Prototyping is appropriate for
(a)
Data-oriented applications
(b)
Applications with emphasis on the user interface
(c)
Applications which are highly interactive
(d)
Development teams who lack domain experience
(e)
All of the above.
37.
What are the major activities of the spiral model of software engineering?
(a)
Planning, Risk Analysis, Engineering, Customer Evaluation
(b)
Defining, Prototyping, Testing, Delivery
(c)
Requirements
(d)
Quick Design, Build Prototype, Evaluate Prototype, Refine Prototype
(e)
Testing.
38.
In choosing a development life-cycle model, one would consider the
(a)
Development Group Expertise, Problem Characteristics, User Expectations
(b)
Languages, Development Schedule, Competition
(c)
System Context, User Population, Platforms
(d)
Organizational Structure, User Tasks, Performance Criteria
(e)
System Analysis, User interface, Testing.
39.
What are the factors to be considered when planning a software development effort?
(a)
Performance, Problem, Product, Planning
(b)
People, Problem, Product, Process
(c)
People, Problem, Productivity, Performance
(d)
People, Problem, Product, Portability
(e)
Productivity, Programming, Performance, Pay-Off.
40.
Which of the following could be a deliverable for a software system?
(a)
Source Code
(b)
Reference Manual
(c)
Requirements Document
(d)
User's Guide
(e)
All of the above.
41.
Which of the following is not viewed as a primary mover in improving the software process?
(a)
Increased Effectiveness
(b)
Better Product Quality
(c)
Improved Staff Satisfaction
(d)
Reduced Costs
(e)
Tighter managerial control.
42.
Symptoms of the software crisis would include
(a)
Software delivered behind schedule
(b)
Software exceeding cost estimate
(c)
Unreliable
(d)
Difficult to maintain
(e)
All of the above.
43.
Which of the following projects would be a good one for adopting the prototyping paradigm for software development?
(a)
Accounting System
(b)
Spreadsheet
(c)
Automobile Cruise Control
(d)
Telephone Switching System
(e)
Algebra Tutor.
44.
Views of quality software would not include
(a)
Optimizing price and performance
(b)
Minimizing the execution errors
(c)
Conformance to specification
(d)
Establishing valid requirements
(e)
Maximizing errors.
45.
Software configuration activities would not include
(a)
Identify change
(b)
Control change
(c)
Ensure improper implementation of change
(d)
Report change to interested parties
(e)
All of the above.
46.
In planning a software project one would
(a)
Find ways to produce results using limited resources
(b)
Pad the schedule to accommodate errors
(c)
Overestimate the budget
(d)
Structure the team to prevent administrative interference
(e)
All of the above.
47.
A systematic approach to software development, as epitomized by the various life-cycle models, is useful in
(a)
Helping us understand the nature of the software product
(b)
Convincing the customer that we know what we are doing
(c)
Filling texts on software engineering
(d)
Managing the various activities necessary to get the job done
(e)
Testing the entire project
48.
A process view in software engineering would consider which of the following
(a)
Product performance
(b)
Staffing
(c)
Functionality
(d)
Reliability
(e)
Usability.
49.
Software measurement is useful to
(a)
Indicate quality of the product
(b)
Track progress
(c)
Assess productivity
(d)
Form a baseline for estimation and prediction
(e)
All of the above.
50.
Which of the following is not a ‘concern’ during the management of a software project?
(a)
Money
(b)
Time
(c)
Product quality
(d)
Project/product information
(e)
Product quantity.
51.
What would be investigated during Requirements analysis?
(a)
System performance , Test Scheduling, Organizational Structure
(b)
Languages , Platforms, Competition
(c)
System Context , User Populations, User Tasks
(d)
Verification, Formal Methods, Accuracy
(e)
Validation, Informal methods, Inaccuracy.
52.
Which of the following is not a description of planning?
(a)
Planning is used to find credible ways to produce results with limited resources and limited schedule flexibility
(b)
Planning is finding new personnel resources to support labor intensive development
(c)
Planning is identifying and accommodating the unforeseen
(d)
Planning is blending the efforts of many people to produce a product that satisfies the customer's need
(e)
Planning is negotiating compromises in completion dates and resource allocation.
53.
The information we need to capture during requirements analysis not include
(a)
Hiring Authority
(b)
Communication Paths
(c)
Synchronization
(d)
Temporal Dependencies
(e)
Data Aggregation.
54.
What do you call when two modules are coupled, when they communicate via a composite data item?
(a)
Content coupling
(b)
Common coupling
(c)
Control coupling
(d)
Data coupling
(e)
Stamp coupling.
55.
Which among the following measures how strongly the elements within a module are related?
(a)
Coupling
(b)
Cohesion
(c)
Aggregation
(d)
Inheritance
(e)
Abstraction.
56.
What do you call, when the elements of a module, all operate on the same data?
(a)
Functional cohesion
(b)
Temporal cohesion
(c)
Procedural cohesion
(d)
Communicational cohesion
(e)
Coincidental cohesion.
57.
Which tests are designed to confront the program with abnormal situations?
(a)
Recovery testing
(b)
Security testing
(c)
Stress testing
(d)
Performance testing
(e)
Usage testing.
58.
To which software category does Knowledge based system belongs?
(a)
System software
(b)
Real time software
(c)
Embedded software
(d)
Personnel  software
(e)
Artificial Intelligent software.
59.
Which is not involved in software development process?
(a)
People
(b)
Problem
(c)
Practice
(d)
Process
(e)
Product.
60.
Which of the following are direct measures?
I.     Size.
II.     Effort.
III.    Schedule.
IV.   Quality.
(a)
Both (I) and (II) above
(b)
Both (I) and (III) above
(c)
Both (I) and (IV) above
(d)
Both (II) and (III) above
(e)
All (I), (II), (III) and (IV) above.
61.
How does a software project manager need to act to minimize the risk of software failure?
(a)
Double the project team size
(b)
Request a large budget
(c)
Form a small software team
(d)
Track progress
(e)
Request for more period of time.
62.
To be an effective aid in process improvement the baseline metrics used must be
(a)
Based on reasonable estimates from failed projects
(b)
Measured consistently across projects
(c)
Drawn from large projects only
(d)
Based only on successful projects
(e)
Drawn from failed projects.
63.
Empirical estimation models are typically based on
(a)
Expert judgment based on past project experiences
(b)
Refinement of current project estimation
(c)
Regression models derived from historical project data
(d)
Trial and error determination of the parameters and coefficients
(e)
Estimation of present data.
64.
Which of the following is not the guiding principle of software project scheduling?
(a)
Compartmentalization
(b)
Market assessment
(c)
Time allocation
(d)
Effort validation
(e)
Interdependency.
65.
The tools for computing critical path and project completion times from activity networks is/are
I.     CPM.
II.     DRE.
III.    FP.
IV.   PERT.
(a)
Both (I) and (III) above
(b)
Both (I) and (IV) above
(c)
Both (II) and (IV) above
(d)
Both (II) and (III) above
(e)
All (I), (II), (III) and (IV) above.
66.
The purpose of earned value analysis is to
(a)
Determine how to compensate developers based on their productivity
(b)
Provide a quantitative means of assessing software project progress
(c)
Provide a qualitative means of assessing software project progress
(d)
Set the price point for a software product based on development effort
(e)
Provide qualitative and quantitative measure of assesing software project progress.
67.
The rapid application development model is
(a)
Same as component-based development
(b)
A useful approach when a customer cannot define requirements clearly
(c)
A high-speed adaptation of the linear sequential model
(d)
Same as incremental model
(e)
Same as water fall model.
68.
Which of the following is not an objective for building analysis models?
(a)
Define set of software requirements that can be validated
(b)
Describe customer requirements
(c)
Develop a solution for the problem
(d)
Establish basis for software design
(e)
Define set of software requirements that can be verified.
69.
The entity relationship diagram
(a)
Depicts relationships between data objects
(b)
Depicts functions that transform the data flow
(c)
Indicates how data are transformed by the system
(d)
Indicates system reactions to external events
(e)
Depicts the physical design of the data.
70.
Which of the following is not an area of concern in the design model?
(a)
Architecture
(b)
Data design
(c)
Interfaces design
(d)
Project scope
(e)
Modular design.
 

71.
Coupling is a qualitative indication of the degree to which a module
(a)
Can be written more compactly
(b)
Focuses on just one thing
©
Is able to complete its function in a timely manner
(d)
Is connected to other modules
(e)
Is able to completed its logic in a timely manner.
72.
Which of the following interface design principles reduces the user’s memory load?
e.         Define intuitive shortcuts
II.     Disclose information in a progressive fashion
III.    Establish meaningful defaults
IV.   Provide an on-line tutorial
(a)
Only (I) above
(b)
Only (II) above
©
Only (III) above
(d)
(I), (II) and (III) above
(e)
All (I), (II), (III) and (IV) above.
73.
Black box testing is also called
(a)
Specification-based testing
(b)
Structural testing
©
Verification
(d)
Unit testing
(e)
Stress testing.
74.
Which configuration objects would not typically be found in the project database?
(a)
Design specification
(b)
Marketing data
©
Executable code
(d)
Test plans
(e)
Test procedures.
75.
Which of the following task(s) is/are not part of software configuration management?
e.         Change control.
II.     Reporting.
III.    Statistical quality control.
(a)
Only (I) above
(b)
Only (II) above
©
Only (III) above
(d)
Both (I) and (II) above
(e)
Both (I) and (III) above.
76.
Which box specification is not associated with cleanroom approach?
(a)
Black box
(b)
Clear box
©
State box
(d)
White box
(e)
Silver box.
77.
Which of the following is not a logical layer of the application in client server system?
(a)
Presentation layer
(b)
Application layer
©
Data Management layer
(d)
Programming layer
(e)
Business layer.
78.
Which of the following is true for a thin-client?
(a)
Processes application logic
(b)
Performs data management task
©
Places heavy processing load on the server
(d)
Makes use of processing power of the client
(e)
Places heavy processing load on the client.
79.
Traditionally, the phase of software development where a formal approach used is
(a)
Programming
(b)
Design
©
Requirements
(d)
Planning
(e)
Testing.
80.
Domain Engineering in CBSE is to
(a)
Identification of components
(b)
Catalogue reusable components
©
Domain modeling
(d)
Structural modeling
(e)
All the above.

Answers

1.
Answer : ©
Reason:  Remaining all are contradictory.
2.
Answer : (d)
Reason:  Software crisis of the late 60’s .
3.
Answer : (d)
Reason:  D is the appropriate choice.
4.
Answer : (a)
Reason:  Evolutionary development usually comes in two flavors; exploratory development, and throw-away prototyping is the correct statement with respect to Evolutionary development.
5.
Answer : (e)
Reason:  The fundamental reason that software can not be considered to be engineered is the complexity of systems and their interaction continues faster than we can understand it.
6.
Answer : (a)
Reason:  In the requirements phase the concept is explored and refined and the clients requirements are elicited.
7.
Answer : (e)
Reason:  The individual or organisation who wants a product to be developed is known as the client.
8.
Answer : (e)
Reason:  The software project management plan should include: the life cycle model to be used, the organisational structure of the development organisation, project responsibilities, managerial objectives and priorities, the life cycle model to be used, detailed schedules, budgets and resource allocations.
9.
Answer : (e)
Reason:  Beta testing occurs when a commercial form of the software is released to selected clients.
10.
Answer : ©
Reason:  Regression testing occurs when the product is tested against previous test cases. This most frequently occurs in the maintenance phase.
11.
Answer : (c)
Reason:  The sole use of the rapid prototype is to determine what the client's real needs are as rapidly as possible. The rapid prototype is then effectively discarded so its internal structure is not relevant.
12.
Answer : (e)
Reason:  There are many risks involved in software development.
13.
Answer : (e)
Reason:  A simple way of looking at the spiral software life-cycle model is as a waterfall model with each phase proceeded by risk analysis.
14.
Answer : (d)
Reason:  The degree of interaction between two modules is known as coupling.
15.
Answer : (b)
Reason:  A derived class inherits all the attributes of a base class.
16.
Answer : (a)
Reason:  In communicational cohesion the output from one element in the component serves as input for some other element.
17.
Answer : (e)
Reason:  You should aim to maximize the interaction within a module and minimize the interaction between modules.
18.
Answer : (c)
Reason:  Two modules are control coupled if one passes an element of control to another.
19.
Answer : (d)
Reason:  The three types of abstraction (data, procedural and iteration) are all instances of the more general concept of information hiding.
20.
Answer : (d)
Reason:  In the classical chief programmer team approach, the team member responsible for maintaining the detailed design and coding is the individual coder (i.e. programmer).
21.
Answer : (a)
Reason:  Internal costs comprise all the costs to the developers.
22.
Answer : (e)
Reason:  There are many problems with using Lines of Code to measure the size of a product.
23.
Answer : (d)
Reason:  Software Science bases its estimation of the size of a product on the number of operands and operators.
24.
Answer : (a)
Reason:  In Intermediate COCOMO there are three modes: organic, semidetached and imbedded.
25.
Answer : (b)
Reason:  Work that continues throughout the project and does not relate to any specific phase of software development is termed a project function.
26.
Answer : (e)
Reason:  There are many advantages of using a standard.
27.
Answer : (b)
Reason:  The best way to test the Software Project Management Plan (SPMP) is by a plan inspection by the SQA team. In order to further reduce risk the duration and cost estimates should further be independently computed by people other than the original project team.
28.
Answer : (e)
Reason:  Cost estimation incorporates a number of factors.
29.
Answer : (e)
Reason:  The aim of software engineering is to produce software that is fault-free, delivered on time, delivered within budget, and satisfies users' needs.
30.
Answer : (e)
Reason:  The first OO language was considered to be SIMULA 67.
31.
Answer : (e)
Reason:  Software engineering is the systematic approach to the   development of software , operation of software , maintenance of software and  retirement of software .
32.
Answer : (c)
Reason:  Brooks’ view of the essence of software included Complexity, conformity, changeability &invisibility.
33.
Answer : (d)
Reason:  The essence of software engineering is managing complexity, personnel resources, time and money and producing useful products.
34.
Answer : (d)
Reason:  Planning is life-cycle concern.
35.
Answer : (a)
Reason:  Process perspective and defect elimination best captures the quality paradigm.
36.
Answer : (e)
Reason:  Prototyping seems appropriate for Data-oriented applications, Applications with emphasis on the user interface, Applications which are highly interactive and Development teams who lack domain experience
37.
Answer : (a)
Reason:  Planning , risk analysis ,engineering and customer evaluation are the important four major activities of the spiral model.
38.
Answer : (a)
Reason:  Choice A is the apt among all the answers  for choosing a development life cycle model.
39.
Answer : (b)
Reason:  People, Problem, Product&  Process factors are considered when planning a software development effort.
40.
Answer : (e)
Reason:  Soruce code, reference manual ,requirements document and user’s guide are the deliverables for a software system.
41.
Answer : (e)
Reason:  Tightermanageiral control is not viewed as a primary mover in improving the software process
42.
Answer : (e)
Reason:  When software delivered behind schedule, software exceeding      cost estimate ,unreliable and difficult to maintain then it is said that software crisis.
43.
Answer : (e)
Reason:  Algebra Tutor would be a good candidate for adoting the prototyping paradigm.
44.
Answer : (b)
Reason:  minimizing the execution errors would not included in views of quality software.
45.
Answer : (c)
Reason:  Software configuration activities would include proper implementation of change.
46.
Answer : (a)
Reason:  In planning a software project I would find ways to produce results using limited resources
47.
Answer : (d)
Reason:  A systematic approach to software development, as epitomized by the various life-cycle models, is useful in managing the various activities necessary to get the job done.
48.
Answer : (b)
Reason:  Staffing is the apt choice among the given
49.
Answer : (e)
Reason:  Software measurement is useful to , indicate quality of the product , track progress , assess productivity  and  form a baseline for estimation and prediction.
50.
Answer : (e)
Reason:  Product quantity would not include during the management of a software project.
51.
Answer : (c)
Reason:  C is the right choice.
52.
Answer : (b)
Reason:  Planning is finding new personnel resources to support labor intensive development is not descriptive of planning
53.
Answer : (a)
Reason:  The information we need to capture during requirements analysis would probably not include hiring Authority .
54.
Answer : (e)
Reason:  Stamp coupling is that when two modules are coupled if they communicate via composite data item.
55.
Answer : (b)
Reason:  Cohesion measures how strongly the elements within a module are related.
56.
Answer : (d)
Reason:  when   the elements of a module all operate on the same data we call it as a communicational cohesion.
57.
Answer : (c)
Reason:  Stress testing is to confront the program with abnormal situations.
58.
Answer : (e)
Reason:  Artificial Intelligent software belongs to knowledge based system.
59.
Answer : (c)
Reason:  practice is not involved in software development process.
60.
Answer : (e)
Reason:  size, effort, schedule and quality are the direct measures.
61.
Answer : (d)
Reason  :       a software project manager need to act to minimize the risk of software failure by Tracking the progress of software
62.
Answer : (b)
Reason  :       To be an effective aid in process improvement the baseline metrics used must be Measured consistently across projects
63.
Answer : (c)
Reason  :       Empirical estimation models are typically based on  Regression models derived from historical project data.
64.
Answer : (b)
Reason  :       Market Assessment  is not one of the guiding principles of software project scheduling:
65.
Answer : (b)
Reason  :       Two tools for computing critical path and project completion times from activity networks are CPM &PERT
66.
Answer : (b)
Reason  :       The purpose of earned value analysis is to Provide a quantitative means of assessing software project progress
67.
Answer : (c)
Reason  :       The rapid application development model is A high-speed adaptation of the linear sequential model.
68.
Answer : (c)
Reason  :       Develop a solution for the problem  is not an objective for building analysis models?
69.
Answer : (a)
Reason  :       The entity relationship diagram depicts relationships between data objects
70.
Answer : (d)
Reason  :       Project Scope  is not an area of concern in the design model
71.
Answer : (d)
Reason  :       Coupling is a qualitative indication of the degree to which a module is connected to other modules.
72.
Answer : (d)
Reason  :       The following Define intuitive shortcuts ,Disclose information in a progressive fashion, Establish meaningful defaults interface design principles reduces the user's memory load
73.
Answer : (a)
Reason  :       Black box testing is another name for  Specification-based testing.
74.
Answer : (b)
Reason  :       Marketing data  configuration objects would not typically be found in the project database
75.
Answer : (c)
Reason  :       the following task Statistical quality control is not part of software configuration management
76.
Answer : (d)
Reason  :       White box specification is not associated with cleanroom approach
77.
Answer : (d)
Reason  :       Programming  is not a logical layer of the application in client server system
78.
Answer : (c)
Reason  :       Places heavy processing load on the server
79.
Answer : (a)
Reason  :       Traditionally, the only phase of software development where a formal approach is used is  Programming.
80.
Answer : (e)
Reason  :       Domain Engineering in CBSE is toIdentification of components,Catalogue reusable components,Domain modeling, Structural modeling.

No comments:

Post a Comment